Donlin Pipeline
Donlin Gold, LLC, submitted a pipeline right-of-way lease application dated April 9, 2014 for the proposed contract carrier Donlin Pipeline. The proposed 14-inch diameter Donlin Pipeline would transport natural gas from the Beluga Natural Gas Pipeline system to the Donlin Gold mine near Crooked Creek. Pipe thickness would be a minimum 0.312", up to 0.406" in HDD locations; final thickness will be determined in final design. The proposed 315-mile-long pipeline will be located across a variety of lands; approximately 207 miles are proposed on State of Alaska land. In addition to a federal environmental review which ended in 2018, the Donlin pipeline preliminary decision was issued for public review in January 2019, followed by 6 public hearings. DNR continues to review the pipeline application for a final decision. Other DNR information available at http://dnr.alaska.gov/mlw/mining/largemine/donlin/
- Donlin Gold, LLC
- Natural Gas
- 14
- 315.00 / 207.00
- 0.312
- 231908
- Buried