| Name | ADL | Status | Operator | Product | Diameter (in) | Length (mi) | Location | Region | Construction Year |
|---|---|---|---|---|---|---|---|---|---|
| Alaska Stand Alone Pipeline | 418997 | Project | Alaska Gasline Development Corporation | Natural Gas | 24.00, 12.00 | 737.00 | Buried | North Slope, South Central | |
| Alpine Diesel | Active | 2.38 | 34.20 | Above Ground | North Slope | 01/01/1998 - 01/01/1999 | |||
| Alpine Oil | Active | 14.00 | 34.20 | Above Ground | North Slope | 01/01/1998 - 01/01/1999 | |||
| Alpine Utility | Active | 12.75 | 34.20 | Above Ground | North Slope | 01/01/1998 - 01/01/1999 | |||
| Badami Sales Oil | Active | 12.75 | 25.10 | Above Ground | 01/01/1998 - 01/01/1998 | ||||
| Badami Utility | Active | 6.63 | 31.00 | Above Ground | 01/01/1998 - 01/01/1998 | ||||
| Endicott | Active | 16.00 | 26.10 | Above Ground | North Slope | 01/01/1987 - 01/01/1987 | |||
| Kenai Kachemak | Active | 12.75 | 46.20 | Buried | Southcentral | 01/01/2003 - 01/01/2004 | |||
| Kuparuk | Active | 24.00, 16.00 | 28.00 | Above Ground | North Slope | 01/01/1984 - 01/01/1984 | |||
| Kuparuk Extension | Active | 18.00 | 9.00 | Above Ground | North Slope | 01/01/1983 - 01/01/1983 | |||
| Milne Point Oil | Active | 12.00 | 10.70 | Above Ground | North Slope | 01/01/1984 - 01/01/1985 | |||
| Milne Point Product | Active | 8.00 | 10.40 | Above Ground | North Slope | 01/01/2000 - 01/01/2000 | |||
| Nikiski Alaska | Active | 10.75 | 52.50 | Buried | Southcentral | 01/01/1976 - 01/01/1976 | |||
| North Fork | Active | 4.50, 4.00 | 7.40 | Buried | Southcentral | 01/01/2010 - 01/01/2011 | |||
| Northstar Gas | Active | 10.15 | 16.40 | North Slope | 01/01/2000 - 01/01/2001 | ||||
| Northstar Oil | Active | 10.75 | 17.40 | North Slope | 01/01/2000 - 01/01/2001 | ||||
| Nuiqsut Natural Gas | Active | 3.50 | 14.40 | North Slope | 01/01/1998 - 01/01/2001 | ||||
| Oliktok Natural Gas | Active | 16.00 | 28.00 | Above Ground | North Slope | 01/01/1980 - 01/01/1981 | |||
| Point Thomson | Active | 12.75 | 22.20 | Above Ground | North Slope | 01/01/2013 - 01/01/2015 | |||
| Trans-Alaska Pipeline System | Active | 48.00 | 800.00 | 01/01/1975 - 01/01/1977 | |||||
| Donlin Pipeline | Project | 14.00 | 315.00 | Buried | |||||
| Alaska LNG GTP-Mainline-LF | Project | 42.00 | 807.00 | Buried | Central | ||||
| Liberty Sales Oil Pipeline | Project | 12.00 | 7.10 | North Slope | |||||
| Liberty Utility Pipeline | Project | 4.00 | 7.10 | North Slope | |||||
| CIGGS Pipeline | Active | 10.75 | 26.00 | Southcentral | 01/01/1972 | ||||
| Tyonek W 10 Gas Pipeline | Active | 10.75 | 7.50 | Southcentral | 01/01/2018 - 01/01/2018 | ||||
| Pebble Pipeline | Project | 12.00 | 188.00 | ||||||
| Alaska LNG Point Thomson Transmission Line | Project | 32.00 | 63.00 | Central | |||||
| Pikka Sales Oil Pipeline | Project | ||||||||
| WNS Products Pipeline | Project | Diesel | 6.00 | 34.80 | Above Ground | North Slope | |||
| Willow Sales Oil Pipeline | Project | Crude Oil | 16.00 | 32.40 | Above Ground | North Slope | |||
| WNS Utility Pipeline | Project | Seawater | 20.00 | 63.80 | Above Ground | North Slope |