The Point Thomson Export Pipeline (PTEP) extends about 22 miles from the Point Thomson Central Pad (CP), located approximately 60 miles east of Prudhoe Bay, to a point of connection with the existing Badami Sales Oil Pipeline at the Badami Central Facilities Pad (CFP). The PTEP lease was issued in 2012, with construction on the pipeline beginning just after. Pipeline construction was completed in 2013, with transportation of product through the line beginning in 2016.


Point Thomson News

There is no current Point Thomson news.

Current Operator
  • Point Thomson Export Pipeline, LLC
Regions
  • North Slope
Original ROW Lease Dates
  • October 31, 2012 - October 31, 2042
Product
  • Crude Oil
Diameter (inches)
  • 12.75
System Length (approx. miles)
  • System Length: 22.20
  • Length on State Lands: 22.20
Normal Wall Thickness (inches)
  • 0.406
Associated ADL Numbers
  • 418975
Positions
  • Above Ground
Year Constructed
  • 2013 - 2015