The North Fork Pipeline begins at the North Fork Production Pad, located 8.6 miles east of Anchor Point, and terminates in Anchor Point. The North Fork Pipeline comprises two segments, 6.25 miles of Fiberspar Linepipe and 1.25 miles standard steel construction. The Fiberspar Linepipe is a composite pipe consisting of an inner thermoplastic pressure barrier reinforced by high-strength glass fibers embedded in an epoxy matrix. Pipeline construction began in October 2010 and completed at the end of February 2011.


North Fork News

There is no current North Fork news.

Current Operator
  • Cook Inlet Energy
Regions
  • Southcentral
Original ROW Lease Dates
  • September 28, 2010 - September 27, 2040
Product
  • Natural Gas
Diameter (inches)
  • 4.5
  • 4.0
System Length (approx. miles)
  • System Length: 7.40
  • Length on State Lands: 6.60
Normal Wall Thickness (inches)
  • 0.61
Associated ADL Numbers
  • 230928
Positions
  • Buried
Year Constructed
  • 2010 - 2011